http://www.winnipegfreepress.com/business/bombers-stadium-delays-prompt-lawsuit-163663276.html
Don Pearson, Stuart Olson president and chief operating officer, said
the subcontractor hired to erect the steel framework for the roof -- he
didn't name the firm -- was supposed to start the work in June of last
year and be done by March of this year.
Instead, it started three or four months late, and won't be finished until the end of this month, Pearson said.
April, May, June, July... thats four months.. you know.. the FOUR MONTHS LATE that they started
Don Pearson, Stuart Olson president and chief operating officer, said
the subcontractor hired to erect the steel framework for the roof -- he
didn't name the firm -- was supposed to start the work in June of last
year and be done by March of this year.
Instead, it started three or four months late, and won't be finished until the end of this month, Pearson said.
April, May, June, July... thats four months.. you know.. the FOUR MONTHS LATE that they started